How should we plan a knitwear order around the Chinese New Year factory holiday?
Chinese New Year is 6 February 2027, but the State Council had not published the 2027 holiday notice on 24 October 2026. Factories set their own closing and restart, so ask them in writing.

We want tees delivered in early spring 2027. The factory says it will close for the New Year holiday but has not given dates, and we cannot find the official 2027 holiday notice. How should we plan the order and what should we ask?
Main answer
Chinese New Year, also called the Spring Festival, falls on Saturday 6 February 2027, with New Year’s Eve on Friday 5 February. The State Council’s national holiday measures give Spring Festival four statutory days, from New Year’s Eve to the third day of the first lunar month, and say a holiday that falls on a weekend gets a substitute day. The actual days off and the make-up working days are set each year in a notice from the General Office of the State Council. At the time this answer was written, on 24 October 2026, the notice for 2027 had not been published, so any calendar that shows exact 2027 days off is a forecast. The notice for 2026 was issued during 2025, so one for 2027 is expected, but its date is not announced.
Dates to plan with now
Until the notice is out, plan around the fixed dates and a wide margin. Factories decide their own closure and restart, which often differ from the official days, so a factory may shut before the legal holiday and restart in stages afterwards. Check the State Council’s notice when it is published and then ask each supplier to confirm its schedule against it in writing.
What to ask the factory
Ask in writing: the last production and loading date before the closure, the date work restarts, the date the full workforce returns, and how it handles orders in progress. Ask the same of your fabric mill, dye house, trims suppliers and printers, because a delay in any of them holds up your order. Ask whether the factory has more orders than usual before the break, as order volume may be higher before a closure.
Two ways to plan
One approach is to finish and ship before the break: place the order early enough that fabric, production, inspection and loading all end before the factory closes. The other is to accept a restart: assume production resumes slowly and add buffer for the weeks after the break, when staff return in stages and supplies are rebuilt. Do not schedule a critical delivery just after the restart.
Inspection and freight
Book pre-shipment inspection before the closure for goods that ship before it, and plan for it again after the restart for goods that finish later. Confirm with your forwarder when cut-offs and loading are possible, as ports, trucking and customs brokers may also be affected. The delivery point in your Incoterms rule decides where risk passes to you, so be clear when the goods are handed over to your carrier.
Protect the contract
Put the agreed completion date, the late-delivery remedy and the plan for materials already in stock into the PO. Do not rely on a verbal date. Ask the factory to confirm the dates again about a month before the break, since closing and restart plans can change, and keep the confirmation with the PO. If the order is large or critical, ask for a weekly production update across the closure period, so that you see early if fabric, trims or printing are behind and can still choose between air freight, a split shipment or a later delivery date.
Sources and further reading
- Hong Kong Observatory – Gregorian-Lunar calendar conversion table of 2027
- State Council of China – National Measures on Holidays for Annual Festivals and Memorial Days (revised, State Council Order No. 795)
- State Council General Office notice on 2026 public holiday arrangements (国办发明电〔2025〕7号)
- ICC Digital Library — Incoterms® 2020 rules for any mode of transport (incl. CIP)
Standards and rules are summarised from their published scope or official guidance. Use the current edition and confirm requirements for your market.
Three perspectives on this question
Purchasing perspective
I'd ask each supplier in the chain for its own closing and restart dates and confirm them in writing before I set the PO date.
Merchandising perspective
I'd put the stock the break might delay into the plan early, rather than depend on a perfect restart.
QC perspective
We'd book inspection around the closure, and re-inspect or check carefully the lots made just after workers return.
Working on a similar program?Send your tech pack, fabric references and test requirements. We reply with a quote and the questions we need answered.
Contact Knitwear BaseRelated products
Related articles
- Clothing Production Lead Time: Where the Weeks Actually Go
- Shipping and Freight for Wholesale Apparel: Sea, Air, and Lead Times
- Shipping Clothes From China: Freight Modes, Incoterms and Landed Cost
- Apparel Fabric Sourcing China: Fabric Selection, MOQ and Mill Lead Time
- Garment Quality Inspection Process: Pre-Production, In-Line and Final Inspection Explained
- Apparel Supply Chain Management: Inventory, Lead Time and Supplier Risk Controls
- Wholesale Hoodies Supplier: Pack-Out, Size Ratios and Reorder Planning
- Wholesale Underwear Supplier: Pack-Out, Size Ratios and Reorder Planning
- When to Order Sweaters: A Seasonal Knitwear Calendar for Distributors
- Knitwear MOQ and Sampling: What to Expect From a Knit Factory